Corcoran St NW, from 14th St to 16th St
Pavement resurface / restoration on Corcoran St
Project status is Completed as of October 30, 2009. Post a comment
-
T St NW, from 17th St to 18th St
Pavement resurface / restoration on T St
Project status is Completed as of September 30, 2009. Post a comment
-
Wallach Pl NW, from 13th St to 14th St
Pavement resurface / restoration on Wallach Pl
Project status is Completed as of September 30, 2009. Post a comment
-
California St NW, from Florida Ave to 18th St
Pavement resurface / restoration on California St
Project status is Under construction as of September 18, 2009. Post a comment
-
Wallach Pl NW, from 13th St to 14th St
Sidewalk construction on Wallach Pl
Project status is Completed as of September 7, 2009. Post a comment
-
Champlain St NW, from Florida Ave to Kalorama Rd (S)
Pavement resurface / restoration on Champlain St
Project status is Under construction as of July 30, 2009. Post a comment
-
Hobart St NW, from Mount Pleasant St to Irving St
Pavement resurface / restoration on Hobart St
Project status is Completed as of June 26, 2009. Post a comment
-
California St NW, from Florida Ave to 18th St
Design on California St
Project status is Completed as of March 26, 2009. Post a comment
-
Champlain St NW, from Florida Ave to Kalorama Rd (N)
Design on Champlain St
Project status is Completed as of March 26, 2009. Post a comment
-
18th St NW, from Massachusetts Ave to Florida Ave
Design on 18th St
Project status is Completed as of March 26, 2009. Post a comment
-
Harvard St NW, from Lanier Pl to 18th St
Pavement resurface / restoration on Harvard St
Project status is Completed as of November 5, 2008. Post a comment
-
Adams Mill Rd NW, from Ontario Rd to Harvard St (E)
Pavement resurface / restoration on Adams Mill Rd
Project status is Completed as of October 22, 2008. Post a comment
-
Columbia Rd NW, from Mintwood Pl to Belmont Rd
Pavement resurface / restoration on Columbia Rd
Project status is Completed as of August 19, 2008. Post a comment
-
Columbia Rd NW, from Kalorama Rd to 19th St
Pavement resurface / restoration on Columbia Rd
Project status is Completed as of August 19, 2008. Post a comment
-
Swann St NW, from 18th St to 19th St
Pavement resurface / restoration on Swann St
Project status is Completed as of August 12, 2008. Post a comment
-
Johnson Ave NW, from R St to S St
Pavement resurface / restoration on Johnson Ave
Project status is Completed as of August 12, 2008. Post a comment
-
U St NW, from 9th St, Florida Ave (E) to Florida Ave (W)
Design on U St
Project status is Active design as of August 8, 2008. Post a comment
-
Euclid St NW, from 11th St to 12th St
Pavement resurface / restoration on Euclid St
Project status is Completed as of August 8, 2008. Post a comment
-
Euclid St NW, from 12th St to 13th St
Pavement resurface / restoration on Euclid St
Project status is Completed as of August 8, 2008. Post a comment
-
Champlain St NW, from Cul De Sac (N) to Kalorama Rd (S)
Pavement resurface/restoration on Champlain St
Project status is Completed as of August 8, 2008. Post a comment
-
Adams Mill Rd NW, from Harvard St (W) to Irving St, Kenyon St
Design on Adams Mill Rd
Project status is Active design as of August 8, 2008. Post a comment
-
18th St NW, from Florida Ave to Columbia Rd, Adams Mill Rd
Design on 18th St
Project status is Active design as of August 8, 2008. Post a comment
-
Q St NW, from 11th St to 14th St
Reconstruction on Q St
Project status is Under construction as of August 8, 2008. Post a comment
-
17th St NW, from Massachusetts Ave to New Hampshire Ave, Swann S
Design on 17th St
Project status is Active design as of August 8, 2008. Post a comment
-
16th St NW, from Van Buren St (S) to V St
Traffic signal work on 16th St
Project status is Under construction as of August 8, 2008. Post a comment
-
16th St NW, from V St to V St
Traffic signal work on 16th St
Project status is Completed as of August 8, 2008. Post a comment
-
Hillyer Pl NW, from 20th St to 21st St
Pavement resurface / restoration on Hillyer Pl
Project status is Completed as of August 8, 2008. Post a comment
-
Caroline St NW, from 15th St to 16th St
Pavement resurface / restoration on Caroline St
Project status is Completed as of August 8, 2008. Post a comment
-
Connecticut Ave NW, from Florida Ave to Florida Ave
Traffic signal work on Connecticut Ave
Project status is Completed as of August 8, 2008. Post a comment
-
Connecticut Ave NW, from Dupont Cir (N) to Beach Dr
Pavement resurface/restoration on Connecticut Ave
Project status is Completed as of August 8, 2008. Post a comment