Road construction projects Ward 5
- Ward 5
- Get more news from this area, plus e-mail alerts and RSS feeds.
-
Kenyon St NW, from Irving St (E) to Park Pl
Pavement resurface / restoration on Kenyon St
Project status is Completed as of October 15, 2009. Post a comment
-
New York Ave NE, from Montana Ave (E) to Bladensburg Rd
Pavement resurface / restoration on New York Ave
Project status is Completed as of September 24, 2009. Post a comment
-
Vista St NE, from South Dakota Ave to Central Ave
Pavement resurface / restoration on Vista St
Project status is Completed as of September 1, 2009. Post a comment
-
Newton St NE, from 18th St to 20th St
Sidewalk construction on Newton St
Project status is Completed as of September 1, 2009. Post a comment
-
V St NE, from Bladensburg Rd, 25th Pl to South Dakota Ave
Pavement resurface / restoration on V St
Project status is Completed as of September 1, 2009. Post a comment
-
12th St NE, from Galloway St to Hamilton St (W)
Pavement resurface / restoration on 12th St
Project status is Completed as of September 1, 2009. Post a comment
-
Brentwood Rd NE, from Cul De Sac (E) to Girard St
Pavement resurface / restoration on Brentwood Rd
Project status is Completed as of September 1, 2009. Post a comment
-
4th St NE, from Franklin St to Harewood Rd
Sidewalk construction on 4th St
Project status is Completed as of August 18, 2009. Post a comment
-
North Capitol St BN, from Hawaii Ave, Rock Creek Chu to Buchanan St
Sidewalk construction on North Capitol St
Project status is Under construction as of August 18, 2009. Post a comment
-
North Capitol St BN, from Buchanan St to Crittenden St
Sidewalk construction on North Capitol St
Project status is Under construction as of August 18, 2009. Post a comment
-
North Capitol St BN, from Buchanan St to Rock Creek Church Rd (N)
Sidewalk construction on North Capitol St
Project status is Under construction as of August 18, 2009. Post a comment
-
North Capitol St BN, from Crittenden St to Rock Creek Church Rd (N)
Sidewalk construction on North Capitol St
Project status is Under construction as of August 18, 2009. Post a comment
-
W St NE, from 13th St, Downing St to 18th St, Montana Ave
Federal aid resurfacing on W St
Project status is Under construction as of July 16, 2009. Post a comment
-
Eckington Pl NE, from Harry Thomas Way to R St
Pavement resurface / restoration on Eckington Pl
Project status is Completed as of June 29, 2009. Post a comment
-
12th St NE, from Rhode Island Ave, Saratoga to Michigan Ave
Pavement resurface / restoration on 12th St
Project status is Completed as of June 22, 2009. Post a comment
-
South Dakota Ave NE, from 30th St (E) to Vista St
Bridge construction on South Dakota Ave
Project status is Under construction as of January 7, 2009. Post a comment
-
Bladensburg Rd NE, from 30th St to South Dakota Ave
Pavement resurface / restoration on Bladensburg Rd
Project status is Completed as of October 30, 2008. Post a comment
-
Rhode Island Ave NE, from 3rd St, W St to Reed St
Bridge design on Rhode Island Ave
Project status is Active design as of October 23, 2008. Post a comment
-
South Dakota Ave NE, from 30th St (W) to Vista St
Bridge construction on South Dakota Ave
Project status is Under construction as of October 22, 2008. Post a comment
-
20th St NE, from Franklin St to Irving St, Rhode Island Av
Pavement resurface/restoration on 20th St
Project status is Completed as of August 8, 2008. Post a comment
-
Rhode Island Ave NE, from North Capitol St to 10th St, Bryant St
Federal aid resurfacing on Rhode Island Ave
Project status is Completed as of August 8, 2008. Post a comment
-
Michigan Ave NE, from North Capitol St to 7th St
Design on Michigan Ave
Project status is Active design as of August 8, 2008. Post a comment
-
31st Pl NE, from Otis St to Eastern Ave
Design on 31st Pl
Project status is Active design as of August 8, 2008. Post a comment
-
Central Pl NE, from Capitol Ave to Gallaudet St
Design on Central Pl
Project status is Active design as of August 8, 2008. Post a comment
-
17th St NE, from Montana Ave (E) to West Virginia Ave
Design on 17th St
Project status is Active design as of August 8, 2008. Post a comment
-
Florida Ave NE, from New York Ave to 3rd St
Reconstruction on Florida Ave
Project status is Under construction as of August 8, 2008. Post a comment
-
Adams St NE, from 18th St to Lawrence Ave
Design on Adams St
Project status is Active design as of August 8, 2008. Post a comment
-
Eastern Ave NE, from Bunker Hill Rd, Randolph S to Michigan Ave (N), Queens C
Design on Eastern Ave
Project status is Active design as of August 8, 2008. Post a comment
-
13th St NE, from Monroe St to Monroe St
Traffic signal work on 13th St
Project status is Under construction as of August 8, 2008. Post a comment
-
9th St NE, from Brentwood Pky to T St
Bridge design on 9th St
Project status is Active design as of August 8, 2008. Post a comment