Pavement resurface / restoration on Vermont Ave

Source
District Department of Transportation
Updated
Daily

More about this section…

This is a road construction project with a publication date of July 31, 2009.

Road construction project details

Location Vermont Ave NW, from N St to O St
Publication date July 31, 2009
Project name FY 06 Federal Aid Citywide Pavement Restoration
Remarks
Miles 0.10
Number of blocks 1
Percent completed 100
Work description Pavement resurface / restoration
Road type Collector street

A street that provides direct service to and from local areas, routing traffic to the arterial street system.

Status Completed
Estimated completion date N/A
Actual completion date July 28, 2009
Estimated start date September 1, 2009

Added to EveryBlock on July 31, 2009.